Independent guide. Not an official government or temple website.

Tracker

Simhastha 2028 preparation tracker: where the works stand

Last updated

Quick answer

As of 25 November 2026, most big Simhastha 2028 works in Ujjain are under construction, with a state deadline of the end of 2027. The Kanh river diversion was about two-thirds dug in June 2026, the Sevarkhedi–Silarkhedi water project has slipped to February 2028, the command-centre contract is unawarded and the new Simhastha Act is untabled.

What is the deadline for Simhastha 2028 works?

Planned opening of the mela

All Simhastha works are due by the end of 2027 “without fail”, with monthly reviews, according to the Simhastha Cabinet Committee meeting of 23 November 2026. It is the fourth deadline: December 2027 was set in September 2025, Diwali 2027 in April 2026 and phased deadlines in October 2026 (51 projects by December 2026, 36 by March 2027, 61 by June 2027 and 23 by October 2027). No official percent-complete figure for the whole programme has been published.

River, water and ghats

The aim is that pilgrims bathe in Kshipra water rather than Narmada water pumped in, as happened in 2016.

ItemStatusAs of
New Kshipra ghats, 29.215 km, ₹778.92 crore: 18.2 km of retaining wall and 7 km of ghats doneUnder construction
Upgrade of existing ghats, 7.8 km, ₹120 croreUnder way, no progress figure
Kanh river closed-duct diversion, 30.15 km, ₹919.94 crore: 8.15 of 12 km of tunnel dug; target September 2027Under construction
Sevarkhedi–Silarkhedi storage, ₹614.53 crore: about 80% done in June 2026; completion now February 2028Delayed
Kshipra water quality: BOD 8–12 mg/L against a bathing standard of 3 mg/L (NGT)Not yet fit

Why it matters. The Kanh diversion keeps polluted water from Indore out of the Kshipra, and Sevarkhedi–Silarkhedi stores monsoon water to release for the baths. A February 2028 finish leaves about a month before the planned opening, too late for a 2027 monsoon fill unless the barrage and pumps work earlier. In August 2026 the National Green Tribunal also ordered Ujjain to stop untreated sewage reaching the river; it expects sewage to rise from about 85 to 350 million litres a day during the mela.

Bridges and roads

ItemStatusAs of
22 new bridges (17 river bridges, 5 rail over-bridges), ₹853.46 croreUnder construction
Indore–Ujjain six-lane highway, ₹1,692 crore: about 80% done; target January 2027Under construction
Indore–Ujjain greenfield four-lane, 48.10 km: awarded December 2025 at a ₹1,089 crore bid cost (re-approved at ₹2,935.15 crore under hybrid annuity); 24-month contractUnder construction, early stage
Ujjain–Jaora greenfield road, 98.73 km, ₹5,017 crore: launched 10 July 2026; target December 2027Started, no progress figure
Two elevated corridors to Indore Gate, ₹945.20 croreApproved; status unclear

The existing Indore–Ujjain road stays open while the six-lane is built. No report of any six-lane section opening had been found by 25 November 2026.

Rail and air

ItemStatusAs of
7 Ujjain-area stations getting holding areas and foot overbridgesUnder way, no costs published
Special trains during the mela: 236 (state figure, total)Planned
Ujjain station redevelopment: may not finish before the mela (Railway Board chairman)Under construction
Datana–Matana airstrip, phase 1: 1,800 m runway for ATR-72 aircraft before the melaPlanned
Jet (A320) flights to Ujjain before the melaNot confirmed
Indore–Ujjain metroNot before the mela

For now, Indore's Devi Ahilyabai Holkar Airport, about 53 km away, remains the main airport. See how to reach Simhastha.

Command centre, security and services

ItemStatusAs of
Integrated Command and Control Centre (ICCC), ₹139.14 crore: tender issued 20 May 2026; bids last due 15 Oct 2026 (per tender listings)No award reported
Police equipment, ₹600 crore (cameras, drones, face identification, cyber kit)Sanctioned
About 60,000 police, 11,500 home guards, 10,000 civil defence volunteersPlanned
Toilets and bathing facilities: about 1.19 lakh toilets, 23,200 bathrooms, toilets every 500 mApproved
Temporary power, ₹387.99 crore; 2,000 buses, ₹45 croreApproved
Published mela hospital, bed and ambulance numbersNot published

The ICCC is meant to tie together CCTV, drones, crowd counts and traffic control. Systems like this usually take a year or more to build and test, so the award date matters for the 2027 rehearsals.

Law and administration

ItemStatusAs of
Madhya Bharat Sinhastha Mela Act, 1955In force
New Simhastha Act (draft of more than 50 sections)Not tabled
Simhastha Mela Pradhikaran chairman (Jagdish Agrawal)Appointed 12 Aug 2026
Mela Adhikari (IAS Asheesh Singh, since April 2025; also Ujjain Divisional Commissioner since September 2025)In post
Mela areaNot notified

The draft Act would make permanent building in the mela area an offence and give the Mela Adhikari temporary land powers. It missed the July 2026 monsoon session; the Assembly's winter session runs 7 to 11 December 2026.

What to watch next

  1. due

    51 projects due under the phased plan; monthly Cabinet Committee reviews begin

  2. scheduled

    MP Assembly winter session opens (to 11 Dec): first chance to table the Simhastha Act

  3. target

    Indore–Ujjain six-lane opening target

  4. target

    Kanh diversion target

  5. deadline

    Overall deadline for all Simhastha works

  6. target

    Revised completion of Sevarkhedi–Silarkhedi

  7. planned

    Planned opening of the mela

Money behind these works is explained on Simhastha budget explained.

Frequently asked questions

Will Ujjain be ready for Simhastha 2028?

The state says all works will be done by the end of 2027. As of November 2026 most big projects were under construction, the water storage project had slipped to February 2028 and the command-centre contract was not awarded, so some items are tight.

Will pilgrims bathe in Narmada water again in 2028?

The plan is to use Kshipra water, through the Kanh diversion and the Sevarkhedi–Silarkhedi storage. Both are unfinished, and the storage project's completion has moved to February 2028, so a fallback cannot be ruled out.

Will Ujjain airport be ready for Simhastha?

The first phase at Datana–Matana, a 1,800 m runway for ATR-72 turboprops, is targeted before the mela. No date for jet flights has been given, so most air travellers will still use Indore.

Will the Indore–Ujjain metro run during Simhastha 2028?

No. The metro's project report says it cannot run before the mela; construction is expected afterwards.

What is the Simhastha Act?

The mela is governed by the Madhya Bharat Sinhastha Mela Act, 1955. A new Act is in draft but had not been approved by the Cabinet or tabled in the Assembly by 25 November 2026.

How many new ghats are being built in Ujjain?

29.215 km of new ghats on both banks of the Kshipra, approved at ₹778.92 crore, plus 7.8 km of existing ghats being upgraded. That gives about 37 km of ghats, against about 8 km counted before the 2016 mela.

Sources

  1. MP's Ujjain Simhastha 2028 gets ₹2,801 crore boost as CM Mohan Yadav clears 33 works, sets 2027 deadline Free Press Journal ·
  2. Simhastha 2028 preparations: Madhya Pradesh projects approved Indian Masterminds ·
  3. Simhastha 2028: Mohan Yadav reviews ₹20,000 crore Ujjain projects Indian Masterminds ·
  4. Mohan Yadav inspects ₹1,697 crore Simhastha 2028 ghat and Kanh diversion projects Indian Masterminds ·
  5. MP Cabinet grants administrative approval of ₹778.92 crore for ghat construction on Kshipra river bank LatestLY (ANI) ·
  6. Divisional Commissioner imposes ₹10 lakh fine on Sevarkhedi-Silarkhedi project contractor Mediawala ·
  7. Shipra to flow perennially before Simhasth 2028: Sevarkhedi-Silarkhedi project 80% complete Amar Ujala ·
  8. NGT orders Kshipra rejuvenation, directs UMC to stop untreated sewage discharge Free Press Journal ·
  9. Simhastha 2028: Ujjain Kumbh preparations, MP government infrastructure Indian Masterminds ·
  10. Indore to Ujjain in 35 minutes: new highway to cut travel time News24 ·
  11. Big infra push: govt approves ₹7,000 crore for roads, bridges, water supply The Hitavada ·
  12. Ceigall India wins ₹1,089 crore Indore–Ujjain greenfield highway project in Madhya Pradesh NBM&CW ·
  13. Madhya Pradesh launches ₹50.17 bn Ujjain-Jaora greenfield highway project Construction World ·
  14. Cabinet okays ₹4,525 crore for Public Works Department road projects Free Press Journal ·
  15. Indian Railways to upgrade 7 stations for Ujjain Simhastha 2028 Amar Ujala ·
  16. Simhastha 2028: 1 crore devotees likely to reach Ujjain by train Free Press Journal ·
  17. MP Cabinet approves acquisition of 437 acres land for Ujjain airstrip's expansion ThePrint (PTI) ·
  18. Datana-Matana airport, Ujjain: development update Indian Masterminds ·
  19. ₹10,000 crore metro project (Indore-Ujjain) Patrika ·
  20. Indore-Ujjain metro only after Simhastha 2028 Free Press Journal ·
  21. RFP for System Integrator, Integrated Command and Control Centre, Volume 1 (NIT USCL/430) Ujjain Smart City Ltd ·
  22. Corrigendum: System Integrator for Integrated Command and Control Centre, Ujjain TenderDetail ·
  23. Madhya Pradesh sanctions ₹600 crore for high-tech Simhastha security in Ujjain Free Press Journal ·
  24. Madhya Bharat Sinhastha Mela Act, 1955 India Code, Government of India ·
  25. Draft new Simhastha law: construction banned in mela area The Sootr ·
  26. Five-day winter session of MP Assembly from December 7 NewKerala (IANS) ·
  27. Simhastha fair authority: Jagdish Agrawal appointed chairman Amar Ujala ·
  28. MP transfers 14 IAS: Asheesh Singh Ujjain Commissioner, Singhasth 2028 IndianBureaucracy.com ·

We link to the primary source wherever we can. Dates show when a source was published or last checked. How we check facts